Project Summary:
The South Eastern Railways of India (SER) is undertaking the construction of Talcher-Bimlagarh Railway Line project in Odisha, India. The project involves the construction of a 289Km railway line from Talcher to Bimlagarh. It includes the construction of 10 major bridges, 52 minor bridges, 71 road under bridges (RUBs), 28 road over bridges (ROBs), stations, the installation of lighting and signaling systems, the laying of railway track. East Coast Railway (ECoR) would lay around 140km of track and the rest would be carried out by the SER.
Client:
East Coast Railway
Scope of Work:
Supply, Installation, monitoring and data acquisition of geotechnical instruments including 3D monitoring as well as Construction Supervision including detailed design of single line BG Tunnel between station Sunakhani and Samal.
Instruments Used:
VW Load Cell, Pressure Cell, Shotcrete / Concrete Stress Cell, Rock Bolt Load Cell, Tape Extensometer, V-Notch (Mechanical type), Strain Gauge, Readout Unit, Optical Target, Convergence Meter, Borehole Extensometer (MPBX), Junction / Switch Box, Inclinometer.